Project Name: Donoe Road Project- Phase 2, St. Thomas
Location: Donoe Road
Contract Cost: $593,545.14
Funding Source: American Rescue Plan Act (ARPA)
Hours: 9 a.m. to 3 p.m.
Summary: V.I. Department of Public Works (DPW) contractor Island Roads Corp. will continue the work on the Donoe Road Repairs project on Monday, Jan. 16. The contractor will mill and pave near the bottom of Donoe Road and into the Weymouth Rhymer Highway intersection. Striping will follow at a later time. Motorists are asked to adhere to onsite flagger directives and traverse the area with extreme caution.