Location: Palm Straede and Murphy Gade (Garden Street), St. Thomas
Contract Amount: $456,976.89
Funding Source: American Rescue Plan Act (ARPA)
Date: March 9, 2023
Hours: 8 a.m. to 4 p.m.
Summary: The Department of Public Works (DPW) is updating the community on rescheduled road work on Palm Straede, also known as Longpath and Murphy Gade in the Garden Street area. Due to a mechanical delay, DPW Contractor – Island Roads Corp. – will now start milling on Thursday, March 9.
All vehicles must be removed from the roadway during project work hours. Any abandoned or parked vehicles will be towed if they are present at the time of road work.
This project is scheduled to be completed within two weeks (March 23).